East unbloced - Bureya hydroelectric plant

12 January 2004



Tatyana Sinitsyna reports on the construction of Russia’s Bureya hydroelectric plant, scheduled for completion in 2009 and promising to cut electricity prices in the far eastern regions of the country


THE BUREYA river runs towards the Russian-Chinese border, cutting through virgin woods, hills and mounds. Before reaching the border it joins the Amur, the largest river in the far east of Russia. A 2GW hydroelectric power station under construction there has been named after the Bureya.

Anatoly Chubais, chief of Unified Energy Systems (UES) – Russia's electricity monopoly – has called the power station a ‘great construction project of capitalism’. On the day the act to commission the Bureya power station's first generating unit was signed, Chubais announced a 10% stage-by-stage reduction of electricity charges in the region.

The Bureya power station is the first large electricity project in post-Soviet Russia. Its importance – on political, social, economic and even moral grounds – is such that President Vladimir Putin attended the commissioning ceremony of its first generating unit on 9 July 2003. He was given the privilege of pushing the button to put the first generating unit on stream.

Energy exports

The power plant is to supply electricity to the energy-hungry far eastern regions, increase the reliability of power supply there and reduce the levels of organic fuel delivered to the area. Experts forecast that in 2004 the station's generating capacities will allow over 1.5Mt of coal to be saved. When Bureya is running at full capacity, this amount will increase to 5Mt a year. The project is also designed to prevent seasonal floods in the Bureya floodlands and in the middle reaches of the Amur. Moreover, there is a foreign-economic aspect: the possibility of electricity exports, in particular to China. By June 2003, US$1.3B had been spent on the construction of the first generating unit.

Experts focused on the Bureya and also on the Zeya, another tributary of the Amur, before World War II, as there were electricity shortages in the area. The region was abundant in natural resources, but they needed to be developed. Accordingly, the Zeya power station was built between 1964 and 1980. The location for the Bureya power project was selected in 1973 - the Talakan site was ideal for a dam - and construction began in spring 1976.

The first problems were of a humanitarian nature. There were several old villages with meagre populations in the area of the future water reservoir. Local people were provided with housing in a new well-developed settlement, while a cemetery was also moved to the new place.

Dam design

The Bureya power station was designed by experts in St Petersburg. As the dam was to be built in an earthquake zone, an expensive concrete monolithic model was chosen. Over 3Mm3 of concrete grout is to be poured into the dam's body, but at the time of writing, only one-third of this task had been completed. When finished, the dam will be 139m high, 765m long, 100m wide at the bottom and 25m wide at the top. The reservoir (which has been called the Bureya sea) measures 256km in diameter and it will hold 20.94km3 of water. The station's total capacity will be 2000MW, and its annual electricity output will be 7.1BkWh. This will help to put an end to electricity shortages in the far east and free the area from its dependence on coal deliveries from other regions.

In the final years of the Soviet era, budgets were not enough to finance major projects. After the break-up of the USSR, economic shock therapy in Russia nearly spelled the end of the project. Work at the construction site dragged on, and the workers, who were not paid for months, frequently went on strike.

In 2000, UES took over the construction project and became its main investor. The Railways Ministry and the federal government also provided some financing. Only then did construction work move into a high gear.

The Bureya power station is an ambitious and technically unique project. Immense permanently sealed water turbines, each weighing 100t, are delivered by a huge Ruslan aircraft to a military airfield located 80km away from the power station and designed for receiving the Russian Buran space shuttle. The first two turbines were brought there on 400t platforms.

Men and machines

Some 5000 people, mostly high-class specialists from all over the country, are involved in the power station's construction. Vadim Vasilevsky, deputy chief engineer of the BureyaGESstroi company, says: ‘this project has virtually saved the Russian hydro-technical engineering school, as in four or five years all the experts would have dissolved in other industries.’

The most up-do-date world technologies are being employed in the construction. The highly computerised equipment in use has practically changed the traditional commissioning concept, says Valery Vasilyev, chief construction electrician.

At this power station the switchgear is on a hilltop, right over the dam. From there electricity will be supplied in the main directions. The station's entire electrical scheme is on the control panel, and one can switch on or off any unit, mechanism or individual tumbler at the touch of a button,’ Vasilyev says.

A special control programme has been designed by Russian engineers together with the IBB company, while optical-fibre lines ensure high-speed parameter processing to control the protection of the generator units and the station's main control panel. The first three units will be put into operation with temporary water lines and at reduced pressure. This technological solution allows the hydro-system's payback time to be considerably reduced.

Timetable

The construction of the Bureya hydroelectric power plant will be completed in 2009, by which time six turbines with an aggregate power of 2GW will be installed. At the time of writing, the project's final price remains unclear.

The programme to commission the second unit practically repeated the process of starting the first one, as both units are highly similar. The second generator, with a 185MW thermal power capacity, was commissioned in November 2003. The next phase of commissioning is currently scheduled for 2004.

Konstantin Pulikovsky, the president's representative in the far eastern federal district, says the launch of the second generator at the Bureya plant would lower the electricity tariffs in the Primorye and Khabarovsk territories, Amur and Jewish autonomous districts, which have traditionally depended on imported coal for their electricity.’The next step is to implement other important projects in the far east,’ Pulikovsky adds.

Yet there is concern about the project’s environmental impacts. There are two independent facilities: the generators, the property of the UES, and the water reservoir, which is federal property. Each of the facilities affects the environment. The impact of the power station, associated with accumulation and discharge of water, mainly affects the lower bay.

According to some environmentalists, the flooding of the reservoir may seriously harm the environment, as the Amur will receive less water. This will affect the system of flood-lands, fish reproduction and navigation.

The lowering of the water level in the Bureya will affect the state of the lakes and marshes near the Khingan Preserve. Botanists believe that the unique Far Eastern lotus growing in Lake Dolgoye will become extinct after the water level goes down.

Power engineering specialists are trying to respond to the environmentalists' concern. The UES management has launched a social and environmental monitoring programme for the period until 2017. It includes observations in seismic activity, meteorology, hydrology, ichthyology, zoology and other areas.

The programme will cost UES around US$1.1M. Eighteen research institutes and environmental organisations are taking part in the monitoring. The programme will allow a comprehensive assessment of social and environmental changes accompanying the construction of the power station to be made, as well as the appropriate corrections in nature management to be introduced in due course.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.