$40m refurbishment for Waitaki project, New Zealand

6 February 2013


The Waitaki power station is the oldest station in the Waitaki hydro system and was built by manual labour as a 'make-work' programme during the 1930s Depression.
The power station has six operational 15MW generating units and generates enough electricity each year for about 62,000 average New Zealand homes.
“The Waitaki power station is an historic part of New Zealand's electricity network and despite it being almost 80 years old and, with the work that we are planning, it will continue to provide reliable and sustainable electricity for many generations to come," said Neal Barclay, Meridian's General Manager Markets and Production.
Meridian will carry out a range of work to ensure the old powerhouse building remains strong and usable. This work includes earthquake strengthening. The architectural-look of the building will be retained.
The four-year project is due to start in April and will involve the site's seventh generation unit, which hasn't operated for a number of years. The company will be upgrading the protection for the existing units to identify and rectify faults as early as possible, and will also be making the intersection to the site safer and carrying out erosion, seismic and flood protection work around the site.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.