Agreement reached for Harris Mill dam

11 October 2006


According to the agreement, Viking Power Services will immediately begin the initial testing and design phase at the Harris Mill plant. The initial phase will include meggar testing the existing generator and evaluating the maximum torque that can generated by the water flow based on measurements provided by NEAE.

Based on the information from initial testing and design phase, Viking will advise NEAE as to the replacement, repair or refurbishment of the existing generator and existing hydro turbine.

Last month, Rohde Island governor Donald L. Carcieri announced plans for a US$1.5M project to replace the old hydroelectric equipment at Harris Mill dam with a view to producing in excess of 10MkWh/yr.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.