Alaska selects site for Railbelt hydro project

3 December 2010


Earlier this year, the Alaska Legislature provided funding to AEA for the preliminary planning, design, permitting and field work for the Susitna project, together with a project on Chakachamna lake, as well as Glacier Fork and other hydroelectric projects on Alsaska’s Railbelt. Primary focus was directed on the two large projects - Susitna and Chakachamna - but AEA has now selected Susitna as the main project with Chakachamna to be considered as an alternative.

“Our goal has been to identify the project that has the best chance of being built,” said AEA Acting Executive Director Mike Harper. “A large hydroelectric project for the Railbelt should not only provide cost-effective, reliable, long-term power; it must help the state meet its goal of producing 50% of our power from renewable resources by 2025. We believe the Susitna Project does all this.”

AEA and its consultants evaluated cost, potential environmental impact and energy production of both projects. Additionally, the evaluations included analysis of both projects to determine if either has a fault that would prevent its licensing and construction.

At this time, neither project has been found to have such a fault. However, the studies determined that while the engineering development of the Susitna Project would cost approximately 50% more than Chakachamna, there is greater risk of significant cost overruns at Chakachamna because of the steep terrain and extensive underground work required.

The evaluations further concluded that the Chakachamna Project has greater environmental impact because the project would require a cross-basin water transfer. It was also determined that Chakachamna energy production would be substantially reduced to allow enough water flow to protect the lake’s significant salmon runs.

In summary, it was concluded that the Susitna Project would produce two to three times more energy and at a lower per unit cost; that Susitna has less likely environmental effects; that the project has fewer licensing and permitting complexities; that it can start sooner and involves simpler construction; and that it has a lower long-term operational risk factor.

Supporting documentation including reports prepared by HDR Alaska, Inc., R&M Consultants / Hatch Acres and Seattle-Northwest Securities Corporation can be accessed by visiting Alaska Energy Authority’s home page, www.akenergyauthority.org.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.