Alstom awarded Suofengying contract

21 January 2003


Alstom's hydro division in China is responsible for this project. The 6.1m diameter turbines will be manufactured in the Tianjin facility, which has the capacity to supply a full range of hydro power generation equipment and control systems, as well as project management expertise.

Hydraulic design and model tests will be performed in the Alstom hydro turbine technology centre in Grenoble, France. The equipment has a 44- month delivery schedule, the first unit being due for commissioning at the end of 2005.

This is the second significant order from Guizhou Wujiang Hydro Power Development Co for Alstom. The company's engineers in China are currently executing an order received in 2001 for the refurbishment of Wujiangdu hydro power plant (3 x 250MW).

Hydraulic model tests were performed recently to the customer's full satisfaction and delivery will begin this year as per schedule.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.