Alstom in Brazil small hydro deal

7 February 2011


alstom’s scope of supply for each project includes two Kaplan “S” turbines – which are specifically developed to fit the needs of small hydro plants – together with two generators, two speed controllers, two voltage regulators, and the assembly and commissioning supervision of this equipment.

The 20MW Pezzi plant will be built on the Antas River, between the municipalities of Bom Jesus and Jaquirana. Commissioning should start in September 2012. The 29MW Serra dos Cavalinhos II SHP will be located in the municipalities of São Francisco de Paula and Monte Alegre dos Campos and commissioning should begin in November 2012.

Equipment for the projects is being manufactured at Alstom’s Taubaté plant.

alstom is actively involved in Brazil’s small hydro market. Among recent achievements, in Rio de Janeiro it successfully implemented a Generation Operation Centre, which is responsible for the remote operation and maintenance of 16 small hydro plants distributed in the states of Goiás, Minas Gerais, Espírito Santo and Rio de Janeiro.

The Pezzi and Serra dos Cavalinhos II projects are part of Brookfield Renewable Power’s plans to install between 100 to 150MW of small hydro per year over the next five years.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.