Alstom to supply La Joya

24 June 2003


Under the terms of the contract, alstom will provide the design, engineering and supply of three 17MW vertical Francis turbines, generators, balance of plant, the ALSPA P320 control system, 138kV substation, as well as erection and commissioning.

The main equipment will be manufactured in the company's facilities in Spain. The plant is scheduled to enter commercial operation in August 2005.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.