This is the first ALSPA P320, an advanced power plant control system developed by alstom, to be installed in Vietnam. The work has already begun and is scheduled for completion in 36 months.

Financed by JBIC of Japan, the rehabilitation project is aimed at restoring the Da Nhim Power Station (commissioned in the early 60s) to its original performance levels. Mitsubishi Electric Corp and Mitsubishi Corporation, the main contractors, are responsible for the rehabilitation of four generators and the associated electrical equipment.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.