Andritz Hydro to supply turbines and generators to Austrian hydro plant

1 February 2017


Andritz Hydro has been contracted by Energie Steiermark to supply the electro-mechanical equipment for a new 18MW hydropower plant to be built in the Puntigam district of Graz, Austria. 

Andritz will deliver two bulb turbines (capacity: 2 x 9 MW) with a runner diameter of 3600mm each, including speed controllers as well as generators and excitation systems. The power plant is designed for a gross head of 9.65m and a flow rate of 200m³/sec, and will be equipped with a fish-ladder.

A major part of the equipment will be produced in Andritz Hydro’s production facilities in Austria, mainly at its generator manufacturing plant in Weiz.

Commissioning is planned for the first half of 2019.

 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.