Andritz JV wins order for Batalha project, Brazil

15 May 2009


The Euro44M (US$59.5M) contract was awarded by Brazilian utility Furnas, which is developing the plant to be fully operational by mid- 2011.

The contract calls for supply of two 26.87MW output Kaplan turbines, generators, governors, exciter systems plus other hydromechanical and electromechanical equipment and cranes. Services including erection and commissioning are also to be provided.

The consortium comprises andritz Hydro Brasil, Andritz Hydro Inepar and IESA Projetos.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.