Astaldi, GyM to build Cerro del Águila project, Peru

7 November 2011


The EPC contract includes the development of a concrete dam, an underground power plant, 9km of tunnels, and 60km of roads accessing the site.

Work on the project – commissioned by Peruvian power distribution company Kallpa Generación - is expected to take four years, with preliminary activities starting this year.

Italian firm Astaldi, which is leading the JV, is currently working on another five projects in Latin America – the 98MW Santa Teresa and 90MW Huanza projects in Peru, 66MW El Chaparral in El Salvador, 125MW Pirris in Costa Rica and the 11MW Chacayes project in Chile.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.