The 30m high, 300m long earth and rockfill embankment dam required 300,000m3 of glacial till, sand, gravel and rock as well as more than 4,000m3 of concrete and 65,000kg of steel.

The original, 30m high dam was completed in 1913, which replaced an earlier 4.5m high structure on Coquitlam Lake. Water from the lake is conveyed by a 3.9km long tunnel to Buntzen Lake, from where it is pssed to a power plant.

Work on the structure, in Metro Vancouver's watershed, was undertaken by JJM Construction. Fish-friendly features include a salmon spawning channel and expanding the rearing pond.The 30m high, 300m long earth and rockfill embankment dam required 300,000m3 of glacial till, sand, gravel and rock as well as more than 4,000m3 of concrete and 65,000kg of steel.

The original, 30m high dam was completed in 1913, which replaced an earlier 4.5m high structure on Coquitlam Lake. Water from the lake is conveyed by a 3.9km long tunnel to Buntzen Lake, from where it is pssed to a power plant.

Work on the structure, in Metro Vancouver's watershed, was undertaken by JJM Construction. Fish-friendly features include a salmon spawning channel and expanding the rearing pond.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.