Bishop Falls refurbishment complete

22 April 2003


The US$46.8M investment, designated the Exploits River Hydro Partnership Project, involves the redevelopment of Abitibi-Consolidated's hydroelectric plants at Grand Falls-Windsor and Bishop's Falls in Newfoundland to increase annual energy production by approximately 140GWh.

Construction at the Grand Falls generating station, which includes the installation of a 27MW turbine unit, is expected to be completed by the end of 2003.

Abitibi-Consolidated will continue to use the existing annual generation at its newsprint mill in Grand Falls-Windsor while the additional energy produced will be sold to Newfoundland and Labrador Hydro under a long-term power purchase agreement.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.