Brazil's CPFL sees Q2 contribution from Campos Novos start-up

17 August 2007


The 880MW Campos Novos plant on the river Canoas in Santa Catarina state generated 575GWh of electricity in Q2 following the completion of reservoir impoundment at the end of January. CPFL Energia holds 48.72% of the plant, which represents potential installed and assured energy of average 429.8MW and 184.1MW, respectively. Expenses incurred for the operational start-up of the plant were US$1.4M.

CPFL Energia is also 51% owner of the 855MW Foz do Chapeco project, which commenced construction last December on the river Uruguai on the border between the states of Santa Catarina and Rio Grande do Sul. The plant is scheduled for commissioning in 2010. The company's share of the project equates to 436.1MW of installed capacity and 220.3 median MW of secured power.

Other projects under construction are in the 360MW Ceran complex - the Castro Alves and 14 de Julho plants - which follow the Monte Carlo plant, opened in 2005.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.