Construction starts on Vietnam plants

9 January 2006


The US$406M Ban Chat has a designed capacity of 220MW and the US$613M Huoi Quang plant should produce 520MW.

Ban Chat is due to begin operation by 2010, where as Huoi Quang should start generating electricity by 2011.

Vietnam’s Deputy Prime Minister Nguyen Tan Dung attended the plants’ opening ceremony, along with representatives from the Ministry of Construction, local authorities and almost 4000 residents of Than Uyen and Muong La districts, where the projects are located.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.