Dessau-Soprin wins Rucatayo contract

20 June 2006


The project, estimated at more than US$70M, includes two turbo-generators with a nominal capacity of 60MW, producing more than 300GWh of electricity per year. Work will include the design of a 36km long 220kV power line to link the plant to an existing substation.

Chilean firm Ingentra, a subsidiary of Dessau-Soprin, will design the project in consortium with EDIC Ingenieros of Santiago. Work, to begin this month, is expected to be completed by summer 2007.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.