DfW loan for Bajina Basta project

19 September 2005


The loan has a five-year grace period and is repayable over 15 years. A tender to select the contractor for the project will be issued early next year, with work to start in spring 2008 and be completed in 2012.

The aim of the project is to modernise the Bajina Basta hydroelectric power plant and secure reliable electricity production for the next 30 years.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.