Dulhasti due online at end of March

7 March 2007


The first 130MW generator was synchronised on 28 February, almost two weeks later than earlier scheduled but the remaining two machines should be in operation by the end of the month, as planned.

Work on the run-of-river project began in the early 1980s. However, construction of the project was interrupted and suffered successive delays for a host of reasons ranging from contractual and financial to construction and political.

Major structures on the project include a 65m high, 186m long concrete gravity dam, a 10.6km long headrace tunnel, a tailrace tunnel almost 300m long, and a power house cavern. The dam diverts flow from the river Chenab to a desilting basin before the water is conveyed to the headrace.

In late January, a fatal accident happened during clearing works in an adit tunnel. A mass of concrete fell from the wall as workers were removing dewatering pipes. Two workers died and up to eight suffered injuries.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.