EBRD cancels loan for Boskov Most hydropower plant, Macedonia

26 January 2017


The European Bank for Reconstruction and Development’s €65 million loan to Macedonian electricity generation utility ELEM for construction of Boskov Most hydropower plant has been cancelled as conditions for disbursement were not met.

The loan for the project in Mavrovo National Park was available for five years but this has now expired, with the loan cancelled with no disbursements given.

The 70MW Boskov Most project  is planned to be located near the town of Debar in western FYR Macedonia. The project is intended to utilise fully the hydropower potential of the tributaries that combine to make up the river Mala Reka and will include a dam and reservoir near the village of Tresonce. Annual generation was forecast to be around 118GWh.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.