Energy losses make Trevallyn flow enhancement costly

23 April 2004


When the dam was built in 1955, Hydro Tasmania's license required it to release 0.43m3/sec of water to flow into the river, but recent studies have shown in stream flow requirements of 1.5m³/sec.

The Trevallyn Power Development is a run-the-river hydroelectric scheme built by Hydro Tasmania outside the Central Highlands, consisting of a concrete gravity dam, which diverts water through a tunnel to the Trevallyn Power Station.

The four generators at the power station have a combined capacity of 80MW and operate on a 112m head, with its tailrace water flowing out into the Tamar at sea level.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.