Enerjisa adds 600MW of hydro in 2013

14 May 2014


Enerjisa has announced that it put seven hydroelectric power plants with a combined installed capacity of 600MW into operation in Turkey in 2013.

The Turkish hydroelectric projects that were commissioned in 2013 were: Dagdelen (8MW), Kandil (207MW), Kusakli (20MW), Köprü (156MW), Sarigüzel (103MW), and in December Çambasi (45MW) and the first unit of Kavsak Bendi power plant (62MW).

The new start-ups brought Enerjisa's installed capacity to 2435MW by the end of 2013, with over half from renewable sources.

The share of renewable energy sources in our installed capacity has risen from "23% to 51% by the end of 2013," said Yetik K. Mert, CEO of Enerjisa.

The remaining two units at the Kavsak Bendi hydroelectric plant have since been commissioned, bringing Enerjisa's installed capacity to 2560MW.

The company, which is 50%-owned by European utility E.ON, says that it is moving towards its goal of having 5000MW of installed capacity by 2015.

E.ON said in its first quarter report that Enerjisa is 'performing well from an operational perspective, although this is being overshadowed by the Turkish lira's exchange rate.'



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.