First unit starts operation at Foz do Chapecó, Brazil

26 October 2010


Work on the project began in March 2007 with the signing of a R$650M contract for the production, delivery and assembly supervision of the plant’s four 213.75MW generator units. alstom is responsible for all plant equipment including turbines, generators, hydromechanical equipment, transformers, voltage elevators, plant control and protection systems, and all auxiliary mechanical and electrical systems.

When completed in February 2011, only three and a half years after work began, the plant will have an installed capacity of 855MW and, on average, 432MW of assured energy – enough to supply 25% of all power needs in the state of Santa Catarina or around 18% in Rio Grande do Sul. The plant features the third largest Francis turbine in Brazil in terms of size (after Itaipu and Tucurui).




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.