Fort Halifax demolition postponed

2 September 2003


FPL has said it would rather surrender its federal license to generate power rather than build a fish lift costing US$4M. FPL told the government that there are no affordable options to provide a permanent fish-passage system for the dam.

FERC has said it will not act on the application for license surrender at this time. Instead, it directed FPL to initiate discussions with the other parties with an interest in the dam regarding fish passage alternatives that would allow continued operation.

Under the terms of a 1998 Agreement, FPL Energy is required to provide fish passage by either a fish lift or dam removal.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.