HCC awarded Loharinag Pala contract

18 August 2006


The scope of work includes construction of a 73m long barrage on the river basin of Bhagirathi; head regulator; river training works; and an underground desilting chamber. The work is scheduled for completion in 40 calendar months and is valued at approximately US$53.03M.

The project's capacity comes from four 150MW units, and it is located in the Uttarkashi district of Uttaranchal.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.