HCC wins another contract on Teesta VI

22 October 2008


HCC was awarded the Lot II contract on the project by Lanco Infra Tech Ltd. The contract value is US$73M.

Construction works in the Lot II package include excavation of twin 16.5km long headrace tunnels. The works are to be completed within 45 months.

Earlier this year the contractor won the Lot IV package on the project. The works involve construction of the underground powerhouse and transformer, two surge shafts (60m high x 16m dia.), four pressure shafts (5.4m dia.), tailrace tunnels and some headrace tubes.

HCC is also working on National Hydroelectric Power Corp (NHPC)'s 160MW Teesta Low Dam-Stage IV project, in West Bengal.

NHPC's 510MW Teesta V plant, in East Sikkim District, went into commercial operation early this year.

Separately, the 1200MW Teesta III plant is under development. Teesta Urja Ltd is to have six turbines supplied by Andritiz, and is to be operational from 2011.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.