Huaneng plans massive investment boost

7 September 2006


Hydro and wind power are expected to comprise 10 - 15% of the company's total mainland capacity, including eight hydro stations along the Lancang river in the southwestern Yunnan province.

The plans to spend as much as Yuan 250B (US$31.4B) will add a combined capacity of 50GW and will increase Beijing-based Huaneng's capacity to more than 80GW. The majority of the investment, which is expected to double the company's installed capacity, is slated for coal-fired generation.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.