Hydro Tasmania drought worsens, cloud seeding talks underway.

7 April 2008


The cloud seeding programme started at the beginning of the month over Tasmania and will look to take opportunities over the Great Lake, Lake Gordon, the Mersey-Forth and the Upper and Lower Derwent storages.

However, the delay in completion of an independent study of the impact of cloud seeding on the West Coast has left out the King and Pieman catchments. In the absence of the report, community concerns in the West Coast over the impact of cloud seeding led to the catchments being left out of the current work.

The ongoing drought in Tasmania has resulted in energy yield from hydro catchments being down to only 18% of normal average for the last five months, which is less than the previous record low of 26%.

Overall, the power utility’s storages are just over 18% full. The rainfall that did come was preserved to some degree due to power market replacement by the Basslink interconnector to mainland Australia and also from gas-fired generation. Locally, though, a few run-of-river stations benefited from up to 80mm of rainfall recently in the west and north of the island.

Net imports of electricity via Basslink this financial year have been the equivalent of approximately 11% of reservoir storage. The utility has imported 1,732GWh and exported 215GWh.

The cloud seeding season continues to November. Hydro Tasmania hopes the talks with West Coast communities will enable their catchments to be included for the next cloud seeding season, in 2009.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.