IMPSA will supply Porce III turbines

28 November 2006


IMPSA will supply the 688MW power plant's four Francis turbines, with a staggered start up scheduled for between September 2010 and the start of 2011.

The US$37M contract comprises: design, manufacturing, testing, packing, shipment, transportation, supply, assembling supervision, site tests and start up, and training on the handling of the required equipment.


Related Articles
US$450M Porce III contract awarded



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.