Joint venture to develop Boguchanskaya

23 June 2006


Chubais’ comments follow the recent signing of a cooperation agreement to construct the Boguchanskaya energy and metals complex with UES subsidiary Hydro OGK and Rusal.

The Boguchanskaya hydro plant will be located on the Angara river in the Krasnoyarsk Region with power generated from 2009 along with the 600,000 tones per annum aluminium smelter.

The cost of completing the hydro plant and smelter is estimated at US$3.6B to be financed 30:70 from Rusal and Hydro OGK respectively. Some US$2.5B is to be attracted from external sources Rusal said in a statement, and by the end of 2006, a credit facility of about US$500M will be put in place.

Investment on the preparatory works for the smelter construction and basic engineering will amount to US$100M by the end of 2006 with works on the construction of the infrastructure totalling US$698M.

Construction of the US$370M Boguchanskaya reservoir will be financed by the Federal government budget funds.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.