Tohoku Electric's Kaminojiri No 2 hydroelectric power plant in Japan started operation on 6 June 2002. Located at Nishiaizu-machi in Fukushima Prefecture, the plant utilises the existing Kaminojiri dam and is located adjacent to the first power station.

The newly operating plant has a maximum water intake of 100m3/sec and utilises an effective head of 15.54m to generate a maximum output of 13,500kW.

Tohoku Electric says that Kaminojiri No 2 employs the world's first vertical shaft bulb turbine.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.