Madeira power link auction opts for DC transmission

9 December 2008


Madeira consists of two hydro power projects - Santo Antonion (3150MW) and Jirau (3300MW). Construction began earlier this year on the Madeira river in the state of Rondonia, and the plants are to commence initial operations from 2012-13. The former project is being constructed by a consortium led by Furnas and Odebrecht, and the latter by a JV led by Suez.

The projects are to be connected to the transmission grid by a link that is approximately 2375km long.

Aneel, the national electricity regulator, has managed the process of auctioning the link to be built in seven lots, A - G, covering the line as well as substations. The longest lines are to be built as part of lots D and G. Each concession is for 30 years.

The auction saw Consorcio Intgracao Norte Brasil awarded lots A, C and G for R$44.75M (US$17.9M), R$144.75M (US$57.8M) and RS173.9M (US$69.5M), respectively. The consortium includes Eletronorte, Eletrosul, Abengoa Brasil and Andrade Gutierrez Part. The lots includes lines and substations

Cymi Holding was awarded lots B and E for R$35.4M (US$14.1M) and R$15.5M (US$6.2M), respectively. The works are primarily for lines.

Lots D and F were awarded to Consorcio Madeira Transmissao, a joint venture of Cteep, Furnas and Chesf, for R$176.25M (US$70.4M) and R$151.8M (US$60.6M), respectively. The lots are, separately, for lines and stations.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.