Mavel turbines for Grodnenskaya project, Belarus

6 April 2010


mavel will supply five double regulated horizontal PIT turbines with runner diameters of three meters, Mavel type KP3000K4, to the project, which is owned by RUP Grodnoenergo. Mavel will also supply generators, hydraulic units, gearboxes and control systems.

Each turbine will utilize the head of seven meters and flow of 60m3/sec. The combined expected installed output will be just under 19MW.

Financing for the project was procured from the Czech Export Bank earlier this year.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.