Minesto's Dragon 12 Kite System en route to Faroe Islands after onshore testing

14 November 2023


Ocean energy developer Minesto has successfully concluded the onshore testing phase for its Dragon 12 kite system, a 1.2MW power generation unit, and the unit is now on en route from the Uddevalla port to the Faroe Islands, marking a significant step towards the final stage of commissioning in Vestmanna.

The shipment process is currently underway as the Dragon 12 makes its journey for the crucial system integration phase at the quayside. While progress has been substantial, there is still essential work to be completed, particularly concerning the installation of the drilled and grouted foundation. This foundational work is a prerequisite for the subsequent offshore installation of the power plant and the initiation of electricity production.

Minesto conducted extensive subsystem verification and testing at its workshop in Göteborg, yielding satisfactory results. The meticulous testing process ensures the reliability and efficiency of the Dragon 12 kite system.

Simultaneously, Minesto reports that the 100kW Dragon 4 has entered stable electricity production mode at the Vestmanna site after undergoing necessary service and upgrades.

 

 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.