More funds for Mosul dam repairs

23 September 2005


Reconstruction work on the earthen dam – the largest dam in Iraq – includes an upgrade of specialised maintenance equipment, seismic monitors, materials and spare parts. A training element is included with the aid package to help make the project self-sustaining in the future.

Completed in 1983, the dam has required maintenance to grout areas of leakage on a regular basis. New automatic grout injection equipment will help eliminate seepage under the dam, while new seismic equipment will monitor the dam’s stability.

An Iraqi contractor has been selected for the repair work, with the US Army Corps of Engineers (USACE) providing engineering and quality-control oversight from the Gulf Region Nort.h.

Mosul dam holds back over 12Bm3 of water for the arid western Ninewah Province, while providing hydroelectricity for 1.7M residents in the Mosul area. Work on the 320MW project is scheduled for completion in early 2006.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.