Nam Theun 1 breaks RCC placement record

16 February 2021


At the end of January 2021, the Nam Theun 1 Hydropower Project in Laos PDR broke the World Record for RCC Placement in a single month.

A quantity of 361,333 cubic metres was placed, with one contractor with a single RCC plant.

The average daily production was 11,656 cubic metres, with a peak of 16,463 cubic metres.

This was achieved by Sinohydro Corporation (the Contractor), with the direction and supervision of AFRY Switzerland Ltd (the Engineers responsible for the design, project management and site supervision of the Project).

The Owner is the Nam Theun 1 Power Company Ltd.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.