New hydro plant for Norway

3 July 2018


Construction firm YIT and Norwegian power company Sunnfjord Energi AS are to build a new hydropower plant in the Sogn and Fjordane County in Western Norway.

Under a €32 million contract, the firms will begin work on the Jølstra plant in July 2018, with completion scheduled for December 2020. The contract covers the construction of a power plant, including water intake, power station and approximately 7km of tunnel.

“We have a strong position in infrastructure construction solutions and services in the Nordic and Baltic countries,” commented Harri Kailasalo, Executive Vice President of YIT’s Infrastructure projects segment. “This contract is a good example of projects where our special expertise in energy sector construction plays a crucial role.”

YIT has previously been involved in a similar hydropower plant in Norway, and has also built power plants and been involved in foundation engineering or renovation work in Sweden and in Finland.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.