NIB to help fund hydro plant in Greenland

27 June 2012


The 22.5MW (3x7.5MW) plant is under construction outside the town of Ilulissat on the west coast of Greenland. The plant will harness the water discharge from two natural glacial lakes.

“This project is of high importance for Greenland as the island is reducing its dependence on energy production from fossil fuels. The new power plant will help increase power generation from renewable sources,” said Henrik Normann, NIB President and CEO.

Project infrastructure includes a 5.5km tunnel, underground powerhouse, a 60kV overhead transmission line, roads and a small harbour.

The first of three turbines at the plant is planned to be commissioned in November 2012 and full operation is planned from September 2013.

The funding agreement was for a 15-year-maturity loan.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.