NYPA completes refurb work on 13th turbine

15 October 2010


Refurbishment of the 14th turbine, which began at the end of September, is expected to be completed in May of next year. The Life Extension and Modernization (LEM) project is scheduled to be completed in its entirety by the middle of 2013.

NYPA began the St. Lawrence LEM program in 1998 to replace or renovate the original major generating equipment in the power project and improve the overall performance flexibility and efficiency of the facility, which has operated continuously since 1958 as a source of some of the lowest cost electricity in the country.

The work has required a highly coordinated effort involving nine major component manufacturers in achieving numerous installation milestones. Among the most significant activities have been the disassembly and removal of the turbines—the major component of the turbine-generator units—and the renovation of their turbine-pit locations to facilitate the installation of the refurbished units.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.