RG&E plans 20% capacity hike over two small hydro plants

10 April 2007


The company, which is a subsidiary of Energy East Corporation, will add 9MW over the next three years to two of its plants - Station 2 and Station 5 - on the Genesee river in the City of Rochester. The plants have a total installed capacity of 49MW.

Planning work is to start this year to increase the capacity of Station 2 from 6.5MW to 13MW. The project will see 5.5MW of new capacity added plus a gain of an additional 1MW from improvement to the existing generator, Energy East said in a statement. The rewind work is due for completion next year, the full upgrade by 2009.

Further generator rewind work is planned for Station 5 at Middle/Lower Falls from mid-2008 to add 1.5MW of capacity.

CEO Jim Laurito said: 'Optimising the output of these plants is also an important step in diversifying the fuel mix for generating electricity.'




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.