Slovenia begins construction on Blanca

17 November 2005


The Blanca project will be the second of five plants proposed for the Sava river and the US$70.3M plant is due to begin operations in 2009. The first, Bostanj, was begun in 2003 and is due to start operations next May while the third, Krsko, is scheduled to begin in 2006.

When completed in 2018 the five plants will produce 6% of the country's installed capacity and more than a fifth of its installed hydro generation.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.