The 2.9MW Rodberg plant has been built between the Nore 1 and Nore 2 plants, and generates electricity using the minimum releases from the Rodberg dam. It is expected to generate an average of 15.5GWh per year.

Statkraft said that the new plant exploits 60% of the gross head between Nore 1 and Nore 2.

The utility has a total of 214 hydro power plants, 144 in Norway and it is looking at upgrades as well as further exploitation at existing sites. It has a goal of further hydro power development in Norway to add up to 2000GWh per year more of electricity to the grid.

At the end of last year the company was given approval to build the Eiriksdal plant in the Hoyanger river catchment. The plant is to generate approximately 100GWh per year, increasing the electricity generated from the catchment by 11% to 1000GWh per year.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.