Table 1

1 January 2000


Projected schedule for refurbishing the third power plant
Activity Start Finish
Refurbish Units G22-24 April 2008 September 2017
Design March 2009 January 2010
Contracting January 2010 August 2011
Construction August 2011 September 2017
Plan and site prep August 2011 June 2013
Refurbish G-24 March 2013 September 2014
Refurbish G-23 September 2014 March 2016
Refurbish G-22 March 2016 September 2017
Refurbish Units G-19-21 To be determined
Refurbish exciters May 2007 October 2014
New governor controls September 2008 October 2014
Replace 236MVA transformers November 2006 November 2012
New 500kV cables February 2009 December 2011



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.