Tunnel breakthrough at Buon Kuop

12 February 2007


The tunnel, which Cavico began in December 2003, is nearly 2967m long and 8.2m wide. Cavico and the project's main contractor, Vinaconex, are working together to complete the remainder of the project.

The company will now focus on completing the concrete finish work for the tunnel, which is valued at approximately US$12.36M over the next two years.

The Buon Kuop project has been valued at approximately US$290M. The construction presents the most complicated geological conditions of any current infrastructure project in Vietnam.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.