Ontario Power Generation, the operator of the facility, is now seeking requests for proposals for the construction of the 10.5km Niagara tunnel project, which will divert and carry water from above Niagara Falls to the power station at Queenston Heights. The successful bidder will have to construct the tunnel as a turnkey project.

Work could begin next year and be completed by 2009, when the additional water delivered will equate to increased generation in the region of 1.6TWh.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.