Turkey - dam and tunnel construction

20 June 2006


International bidding will be carried out through the restricted tender procedure among invited candidates considered eligible by the contracting authority following the pre-qualification evaluations.

Work will include construction of the 109m high Bagbasi concrete faced rockfill dam and Mavi tunnel, which has an interior diameter of 4m. As part of the Mavi Tunel construction, 17.061m will be bored by YBM, with the remaining 995m bore by the conventional method. The project is located at Hadim district in the Koyna province of Turkey.

Work is scheduled to start within 30 days following the notification date of the signed contract and should be completed in 1800 calendar days following the job site hand-over.

The pre-qualification documents may be inspected and purchased upon payment of a non-refundable fee of 1000YTL (New Turkish Lira) from: Ismet Inonu Bulvari 06100 Yucetepe/Ankara/Turkey. Tel: +90 312 417 2366. Fax: +90 312 418 3413. Email: adundar@dsi.gov.tr.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.