UES publishes wish list

27 February 2007


The total investment programmes will reach RUB3.1 trillion (US$119 billion) with UES companies spending over RUB1.8 trillion (US$69 billion) on new power projects.

According to UES, its hydro arm, HydroWGC, will need 45 hydro turbines with a combined capacity of 5,000 MW, 43 generators, and 18 transformers with a capacity of 3,500 MW. A further 25 hydro turbines with the combined capacity of 252 MW and 25 generators are also needed to modernize small-scale hydro plants, the company says.

By 2011, collectively UES intends to build 34,200 MW of new generating capacity.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.