Ukrhydroenergo intensifies preparations for winter amid equipment challenges

30 October 2023


Ukrhydroenergo is working to ensure a stable electricity supply to consumers during the upcoming autumn-winter season while grappling with unique equipment challenges, according to Oleg Terletsky, a member of the Supervisory Board of Ukrhydroenergo. Terletsky addressed these critical issues during the 8th Ukrainian Gas Forum, themed "New Energy Architecture of the World and Green Transition," where a panel discussion focused on "Restoring the Ukrainian Energy Infrastructure."

Ukrhydroenergo relies on bespoke, long-production-cycle equipment, making replacement and modernization a complex task. Despite these obstacles, the company is pushing forward with preparations for the winter season, striving to ensure reliable equipment operation and support for the energy system operator.

Terletsky explained, "Our equipment is individually designed and manufactured for us, and this sometimes poses a challenge for replacement or modernization. We are making every possible effort, including lobbying for expediting these processes. We are in the final stages of our winter preparations. Ukrhydroenergo is doing everything to maintain the reliability of our equipment, which is crucial for the stable and uninterrupted operation of our energy system."

All Ukrhydroenergo stations remain operational, except for the Kakhovka Hydropower Plant (HPP), which was destroyed on June 6th.  Ukrhydroenergo's primary objective is to maximize the utilization of the hydroelectric potential of the Dnipro and Dniester rivers. The destruction of Kakhovka HPP's hydro facilities has led to the loss of drinking water equivalent to Ukraine's annual freshwater consumption.

Upon the liberation of the left bank of Kherson, Ukrhydroenergo plans to initiate the construction of temporary hydrotechnical structures. These structures will enable water accumulation in the Kahovka reservoir and provide access to the damaged Kakhovka HPP.

Once a thorough assessment of the damage is completed through technical evaluations and investigations, the company will make an informed decision regarding the restoration of the Kakhovka HPP.

In addition to addressing immediate challenges, Ukrhydroenergo continues to work on long-term projects aimed at modernizing and improving the efficiency of existing equipment. These projects include the construction of the third stage of the Dniester Pumped Storage Power Plant and the development of energy storage systems to enhance flexibility and mobility. The company is also preparing for a pilot project focused on green hydrogen production, aligning with sustainable energy goals.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.