Upgrade for Capanda project

26 October 2006


The work will be carried out in 2007, and will involve adding another 260MW to the current level of 180MW. The first turbine is to be installed in April 2007 and the second will follow a few months later in July.

When the Capanda project is completely finished it will have a capacity of 520MW, to supply power to Angola's northern system, connecting it with the country's central and southern systems.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.