Vietnamese hydro plant inaugurated

4 June 2002


The Yaly hydro power plant, Vietnam's second largest after the Hoa Binh hydro plant in Northern Vietnam, was inaugurated in April 2002.

Construction of the 720MW plant began on 4 November 1993 on the Se San river through the Gai Lai and Kon Tum central highlands provinces. It was designed to include four turbines to generate 3.68BkWh on average annually.

With a total investment of US$554M, the plant has been built by Vietnamese companies with technical support from Russian and Ukrainian experts.

The plant's first turbine was made operational in May 2000 and all of its four turbines generated electricity into the national grid at the end of 2001, according to Electricity of Vietnam (EVN).

The Yaly plant will produce more than 10% of Vietnam's annual electricity output and will help boost socio-economic development in the Central Highlands, EVN said.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.