Voith Hydro to overhaul Swiss utility’s generator fleet

11 October 2010


The contract – the largest individual order in the power plant overhaul project – will involve work on KHR’s four hydro plants. The Sils (4x60MW) and Baerenburg (4x55MW) plants use vertical high-pressure Francis-units, the Ferrera project uses horizontal pump-storage units with motor-generators (3x63MW turbine capacity, and an overall pumping capacity of 90MW), while Thusis is a two unit small hydro power plant (2 and 4MW respectively).




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.